Mepco New Connection – [Step by Step guide]

New Connection Procedure

Obtaining a new Mepco meter connection is a straight forward process. Here’s a step-by-step guide to help you navigate the procedure:

1. Fill out the Online Application Form:

Start by visiting the official Mepco website and find the online application form. Select the type of electricity connection you need and ensure that you choose “MEPCO” from the Distribution Company list. Complete all the required fields in the form.
Download the Mepco New connection form

2. Upload Scanned Copies of Documents:

Prepare scanned copies of the following documents and upload them along with your application:

  • Proof of ownership
  • An undertaking by the applicant
  • Power of attorney (if there are multiple owners)
  • No Objection Certificate (NOC) for tenants
  • Attested copy of the applicant’s CNIC
  • Attested copies of CNIC of two witnesses (not needed for single-phase connections)
  • A copy of the relevant tariff document, duly signed by the consumer

3. Submit the Application Form:

After filling out the application form and attaching the required documents, submit the form online.

4. Get a Printed Copy of the Application Form:

Once you’ve submitted the form, obtain a printed copy for your records.

5. Attach Copies of Required Documents:

Make sure to attach copies of all the required documents to your printed application form.

6. Send the Application and Attachments:

Send the completed application form and attached documents to the Mepco office that corresponds to your location.

7. Receive Demand Notice:

After verifying your documents, you will receive a demand notice, indicating the required fees.

8. Pay the Demand Notice:

Visit the designated bank to pay the demand notice. Remember to keep a copy of the paid demand notice.

9. Submit a Copy of the Paid Demand Notice:

Return to the Mepco office and submit a copy of the paid demand notice.

10. Meter Connection Installation:

Once the payment is verified, Mepco will proceed to install the meter connection.

Checking Application Status and Bills:

If you want to check the status of your new connection application or view your Mepco bill for the new connection, you can either visit your nearest Mepco office or contact their helpline for assistance.

Estimated Time for New Connection:

The time it takes to acquire a new Mepco meter connection depends on the connection category, which is primarily based on the load requirements:

Category 1 (Up to 15 kW):

  • Estimated Time: Approximately 30 days

Category 2 (16 to 70 kW / 400 volts):

  • Estimated Time: Up to 44 days

Category 3 (71 to 500 kW / 400 volts):

  • Estimated Time: Up to 73 days

Please note that the timeframes are approximate and can vary based on various factors. It’s essential to be patient and stay in communication with Mepco during the process to ensure a smooth and timely connection.